Oxfordshire County Council identified the need to replace Kennington Bridge in 2019. As further design and planning work was required before construction could begin, the bridge needed to be carefully managed in the interim. Mabey Hire’s propping and monitoring systems have supported Milestone Infrastructure in maintaining the stability and safety of the structure during this period.
Chris Sadler, Principal Engineer at Milestone Infrastructure (now M Group Highways), explained: “Mabey Hire’s propping scheme was installed in between the in-situ columns, with seven props used to support the bridge deck. We used a mixture of Mabey Hire’s Mat 125 propping and Hymat hydraulic jacks, with its in-house design team drawing up a concept design based on our requirements.
“This design was then developed in AutoCAD and an analysis model in CADS A3D MAX for the anticipated load combinations. Due to the long-term nature of the equipment installation, each prop was designed to a 65 tonnes loading capacity, with Mabey Hire’s jacking experience integral to ensuring the equal load distribution of the bridge deck.”
Due to the structural concerns that had triggered the works and the fact that the bridge was remaining open to traffic throughout, it was essential that Milestone had continuous insight into the bridge’s condition and behaviour.
Chris explained: “As well as the propping and jacking scheme delivered by Mabey Hire, we also utilised their monitoring solutions and expertise. This provided us with invaluable insight, ensuring we had an understanding of how the structure was behaving, and gave us forewarning of future damage, should loads exceed pre-approved limits.”
Learn more about Insite real-time monitoring
To gain more information about the structure, we installed a range of our wireless monitoring sensors onsite, programmed to measure the bridge bearings in two axis, as well as tilt sensors to measure the change of movement on the pier crossheads and abutments. The entire system was installed by our site engineers over the course of planned rail possessions spanning multiple weeks. This was then connected to our unique web portal, with automatic alerts sent to key stakeholders at Milestone and Oxfordshire County Council should limits be breached.
Speaking about working with us, Chris said: “Mabey Hire have been really helpful throughout this whole process. Its live portal, in particular, is a great tool from an asset management perspective, ensuring that both the Council and ourselves are up to date with the bridge’s condition. We also receive monthly data reports from Mabey Hire’s monitoring team, which we use for benchmarking purposes and for presenting to other stakeholders.
Get in touch
For all project specific design and technical enquiries, please contact your local service team
If you want to talk to us about your project, send us an email and a brief outline of how we can help and we’ll be in touch
action@mabeyhire.co.uk
“Mabey Hire are really easy to work with and the team have undergone multiple site visits to check on the equipment and its performance, as well as assist with other elements of the temporary works scheme (not delivered by themselves) in the early stages.”